Below are the updates for the Bolton Construction Works:
Highway 50 and Columbia Way
Asphalt painting underway
All trees and shrubs planted
Terraseeding is near complete…takes 3 days and 2 are completed
Road asphalt scheduled for second week of July to close the project off
Humber River Crossing
Nothing…in maintenance mode
Downtown core watermain and park construction
Foundation has been completed.
Electrical conduits and pot lights being placed this week and early next
The actual pavilion structure will be erected Tuesday and Wednesday with forming of concrete deck late next week
King street Tunnelling
Tender date of July 5th has been established so we are on schedule for September mobilization
Deal reached with Enbridge for Peel to relocate gas lines within the Peel contract
Hydro to be relocated in August.
Water Tower
Under construction.
Major items are:
Storm water Pond near completed
Foundation for the tower being excavated
By the next months update the foundation will be poured