A reminder that Region of Peel will be commencing construction activities for the Bolton Feedermain along King St. from Deer Valley Dr. to the parking lot downtown at the corner of Ann St. and Sterne St.
The main components of the project include:
Construction of a 600mm watermain using microtunnelling technology
Reconstruction and urbanization of Ann St., Sterne St. and the town parking lot including repaving, curbs, sidewalks, landscaping, lighting and electrical car charging stations
Water pressure zone realignment for the areas of Foundry St. west of Hilltop Ct., Deer Valley Dr. north of King St., Bambi Tr. and Doepath Way. These areas will be realigned from Zone 5 to a new Zone 5.5. Residents will see an average increase of 15psi for the water service.
The bulk of the pre-construction paperwork and meetings for this phase of the Feedermain project have taken place and the real construction is about to begin next week. Completion is expected before summer 2014.